LKE Presentation XII International Conference on Lithium
Released
Released
Announcement PDF
10 August 2023
Lake Resources to Present at The XII International Seminar
on Lithium on August 10th, 2023
Executives to Provide Details on Flagship Kachi Project at
Leading Lithium Industry Event Held in Salta, Argentina
Lake Resources NL (ASX: LKE; OTC: LLKKF) (Lake) announces that company executives will
present at The XII International Seminar on Lithium in the South American Region (Seminario
Internacional de Litio en la región de Sudamérica).
In addition to sponsoring this important industry event, Lake executives will present to attendees
on August 10, at 15:50 p.m. ART (GMT-3), providing details on the company’s flagship Kachi
Project, including the recent operational update on the new phased approach to delivering
maximum plant capacity of 50,000 tpa (refer to ASX announcement on June 19, 2023) as well
as the innovative, sustainable DLE process that will be used to produce high purity lithium
carbonate.
Held this year in Salta, Argentina, the annual event is hosted by Panorama Minero and brings
together over 800 participants from major mining companies, suppliers, technology
manufacturers, local and international institutions, and authorities across the lithium value chain.
The agenda for this year’s conference covers:
•
•
•
•
•
•
•
•
•
Global economic situation and geopolitical analysis 2023-2030
Panorama of the region and the main producers
Analysis of the pre-election political-economic situation in Argentina
Global lithium market: review of prices and expectations of supply and demand
Status of the lithium industry in Australia, Chile, China and the United States
Electric vehicle industry news
Critical Minerals and Battery Production Considerations
Use of water and technologies linked to the preservation of the environment
Lithium, environment and decarbonization
Lake will be represented at the conference by Country Manager, Amalia Sáenz, Hydrogeology
Manager, Christian Vega, and Senior Vice President of Technology, Strategy and Risk, Scott
Munro.
About Lake Resources NL
Lake Resources NL (ASX:LKE) (OTCMKTS:LLKKF) is a clean lithium developer utilising stateof-the-art ion exchange extraction technology for production of sustainable, high purity lithium
from its flagship Kachi Project in Catamarca Province within the Lithium Triangle in Argentina
among three other projects covering 220,000 ha.
This ion exchange extraction technology delivers a solution for two rising demands - high purity
battery materials to avoid performance issues, and more sustainable, responsibly sourced
materials with low carbon footprint and significant ESG benefits.
Contact:
Investor Relations:
Karen Greene,SVP, Investor Relations and Communications
karen.greene@lakeresources.com.au
Media:
Nigel Kassulke at Teneo
M: +61-407-904-874
E: Nigel.Kassulke@teneo.com
###
Kachi Reset & Update
August 10, 2023
2
Disclaimer
General Statement and Cautionary Statement
This presentation has been prepared by Lake Resources N.L (Lake) for information purposes and meetings with sophisticated and professional investors, institutional investors and brokers and not any particular party. The information
in this presentation is based upon public information and internally developed data and reflects prevailing conditions and views as of this date, all of which are accordingly subject to change. The information contained in this
presentation is of general nature and is not intended to address the circumstances of any particular individual or entity. There is no guarantee that the information is accurate as of the date it is received or that it will continue to be
accurate in the future. No warranties or representations can be made as to the origin, validity, accuracy, completeness, currency or reliability of the information. No one should act upon such information without appropriate
professional advice after a thorough examination of the particular situation. Lake Resources NL accepts no responsibility or liability to any party in connection with this information or views and Lake disclaims and excludes all liability
(to the extent permitted by law) for losses, claims, damages, demands, costs and expenses of whatever nature arising in any way out of or in connection with the information, its accuracy, completeness or by reason of reliance by any
person on any of it. The information regarding projects described in this presentation are based on exploration targets, apart from the Kachi project’s resource statement. The potential quantity and grade of an exploration target is
conceptual in nature, with insufficient exploration to determine a mineral resource and there is no certainty that further exploration work will result in the determination of mineral resources or that potentially economic quantities of
lithium will be discovered. Some leases are located within and around the Orocobre, Orocobre/Advantage Lithium and Ganfeng/Lithium Americas projects and although data is limited within the properties, the leases may cover
potential extensions to the Cauchari/Olaroz projects with potential extensions to aquifers, although this provides no assurance that any resource will be identified on the Lake leases. The lithium pegmatite leases occur adjacent to
past producers of spodumene but no potential extension to any mineralisation can be assured.
Forward Looking Statements
Certain statements contained in this announcement, including information as to the future financial performance of the projects, are forward-looking statements. Such forward-looking statements are necessarily based upon a
number of estimates and assumptions that, while considered reasonable by Lake Resources N.L. are inherently subject to significant technical, business, economic, competitive, political and social uncertainties and contingencies;
involve known and unknown risks and uncertainties and other factors that could cause actual events or results to differ materially from estimated or anticipated events or results, expressed or implied, reflected in such forwardlooking statements; and may include, among other things, statements regarding targets, estimates and assumptions in respect of production and prices, operating costs and results, capital expenditures, reserves and resources and
anticipated flow rates, and are or may be based on assumptions and estimates related to future technical, economic, market, political, social and other conditions and affected by the risk of further changes in government regulations,
policies or legislation and that further funding may be required, but unavailable, for the ongoing development of Lake’s projects. Lake Resources N.L. disclaims any intent or obligation to update any forward-looking statements,
whether as a result of new information, future events or results or otherwise. The words “believe”, “expect”, “anticipate”, “indicate”, “contemplate”, “target”, “plan”, “intends”, “continue”, “budget”, “estimate”, “may”, “will”,
“schedule” and similar expressions identify forward-looking statements. All forward-looking statements made in this announcement are qualified by the foregoing cautionary statements. Investors are cautioned that forward-looking
statements are not guarantees of future performance and accordingly investors are cautioned not to put undue reliance on forward-looking statements due to the inherent uncertainty therein. Lake does not undertake to update any
forward-looking information, except in accordance with applicable securities laws.
Compliance Statement
The information contained in this presentation relating to financial forecasts, production targets, exploration results, Measured, Indicated and Inferred resource estimates, project execution, infrastructure and testing work, has been
derived from the information in Lake’s JORC update announced on ASX on 15 June 2023. Lake Resources N.L. confirms that it is not aware of any information that materially affects the information included in Lake’s JORC update
announced on ASX on 15 June 2023 and all material assumptions contained in that announcement continue to apply and have not materially changed. On this basis, Lake confirms that the Competent Person’s findings in Lake’s JORC
update announced on ASX on 15 June 2023 have not changed nor been modified in any material respects since that announcement.
Company Overview
Lake Resources NL (ASX:LKE; OTC:LLKKF) is a responsible developer of lithium
from its flagship Kachi Project, in the Catamarca Province of Argentina, in
addition to owning three other lithium brine assets in Argentina. We have an
international team with extensive experience in mining and the development of
large-scale, complex projects located across our offices in Australia, Argentina
and United States.
Focus of Operational Update:
§ Significant Resource Growth
§ Phased Approach to Production
§ Fastest Path to First Lithium
OUR VISION
To become
a growing
contributor
to the energy
transition by
producing high
purity lithium,
operating
sustainably and
improving lives
3
Amalia Saenz
Christian Vega
SVP, Country Manager
& Argentina
Corporate Affairs
Hydrogeology
Manager at Kachi
4
Argentina’s Significant Lithium Assets
Kachi – Lake’s Flagship Project
§ Located in Catamarca region, within the Lithium Triangle which holds ~56%
of the world’s lithium reserves1
§ Government is committed to speedily developing the country’s lithium
resources, with investments in Argentina’s lithium sector
§ Strong relationship with the provincial government of Catamarca. We have
had recent site visits by the Governor of Catamarca and the UK Ambassador
to Argentina and continue to nurture relationships with other key
stakeholders in the government
Notes:
1. US Geological Survey (USGS)
5
6
Strong Community Engagement
Building a strong relationship
with surrounding communities
§ Daily work to maintain and monitor Lake’s Social
License to Operate
§ Committed to ensuring our people and our project
are understood and accepted by all members of the
communities in which we plan to operate
§ Held first Public Information Meeting in May which
was well attended by the local community, and the
information we shared was well received
§ Have obtained new jobs for members of the
Carachi Pampa community
§ Working with provincial authorities to promote
essential training for the community and the
development of the project
§ Emphasis on trainings directly related to the future
construction phase
7
Project Kachi
A New, Phased
Approach
8
Project Concept Reset
Track record of achievement over nine months
Notes:
1. DLE = Direct Lithium Extraction
2. Refer to ASX announcement dated 11 January 2023
3. Refer to ASX announcement dated 12 January 2023
4. Refer to ASX announcement dated 12 January 2023
5. Refer to ASX announcement dated 4 April 2023
9
10
Project Concept Reassessment & Validation
Outcome of Preliminary Assessment
Gaps identified in the following areas
§ Power supply and demand
§ Resource knowledge and reservoir performance
§ Logistics and supporting infrastructure
§ Relationship with our technology partner
§ Rigor of project concept selection
Project Reset has delivered
§ Brine to lithium carbonate process certainty
§ Stronger relationship with technology partner, Lilac,
now integrated into the team
§ Robust plan for completion of reservoir testing
§ Progress in securing a power solution
§ Re-evaluated project concept and selection of lowerrisk delivery option
Notes:
1. Based on maximum plant capacity over two phases and on the information in Lake’s JORC update announced on ASX on 15 June
2023 (Measured 2.2Mt, indicated 0.7Mt, inferred 5.18Mt, exploration target 5.2Mt – 21.8Mt). All material assumptions continue to apply
and have not materially changed. Not an actual ‘production target’ (as defined in the ASX Listing Rules), which is subject to completion
of a bankable DFS.
tpa = tonnes per annum DFS = Bankable Definitive Feasibility Study
Phased development to target
plant capacity of 50,0001 tpa
battery grade lithium
carbonate
§ Two phases of 25,000 tpa each
§ Initial DFS for Phase 1 targeting capacity for 25,000
tpa battery grade lithium carbonate
§ Structured as 2 x 12,500 tpa trains
§ DFS for Phase 1 targeting completion in
December 2023
§ Revised to address selected concept
§ Completing hydrogeological assessment
§ Delivering certainty on power solution and
resource data
§ De-risked project delivery plan
§ DFS for Phase 2 targeting completion by Q4 2026
delivering capacity for another 25,000 tpa battery
grade lithium carbonate
New Path to First Lithium
New Production Plan: Two Phases to 50Ktpa Target Capacity1
50
40
Phased multi-train approach de-risks project
execution “design-1-build-many”
P
O
Reduced reliance on grid connection for plant
startup
P
O
20
Enhances productivity from lessons learned
P
O
10
O
Phased ramp-up demonstrates impacts
acceptable to regulators and facilitates permitting
of future phases
Phase 1 - 25Ktpa
2035+
P
2034
Greater operational resilience (multi-train)
2033
O
2032
P
-
2031
Provides optionality on plant size and product
type with adaptability to prevailing market
conditions for subsequent phase
30
2030
O
Planned modular plant expansion (Ktpa LCE)
2029
P
Old Plan
2028
Fastest path to first lithium production
New Plan
2027
Production Plan
Phase 2 - 25Ktpa Expansion Option
Note
. Target is based off information in Lake’s JORC update announced on ASX on 15 June
2023 which provides an update on mineral resource estimates and exploration targets. See
next slide for further information. Not an actual ‘production target’ (as defined in the ASX
Listing Rules), which is subject to completion of a bankable DFS.
1
P
O
Ktpa = thousand tonnes per annum
LCE = Lithium Carbonate Equivalent
11
Kachi Development Timeline
Key Milestones Targeted
Timeline
2023
Q1
Q2
Q3
2024
Q4
Q1
Q2
Q3
2025
Q4
Q1
Q2
Q3
2026
Q4
Q1
Q2
Q3
2027
Q4
Q1
Q2
Q3
2028
Q4
Q1
Q2
Q3
2029
Q4
Q1
Q2
Q3
2030
Q4
Q1
Bankable DFS Completion for Phase 1 (25Ktpa) Dec. 2023
EIA Submission
Q1 2024
FEED
Q1 – Q3 2024
Financing Activities
Q1 – Q4 2024
EIA Approval
Q1 2025
Decision to Mine (FID) for Phase 1 – 25Ktpa
Q1 2025
EPCM and Commissioning
Q1 2025–Q3 2028
Grid Power Available
Q3 2027
First Lithium Carbonate
Q3 2027
Ramp Up for Phase 1 (25Ktpa)
Q4 2027–Q3 2028
Phase 1 Fully Operational
Q4 2028+
Phase 2 DFS / EIA Approval
Q2 2026–Q3 2027
Phase 2 FID to Fully Operational (25Ktpa)
Q4 2027–Q3 2030
Note: DFS = Definitive Feasibility Study
EIA = Environmental Impact Assessment
Phase 1
Phase 2
FEED = Front End Engineering & Design
FID = Final Investment Decision
EPCM = Engineering, Procurement and
Construction Management
12
Q2
Q3
Phased Approach Reduces Risk And Unlocks Value
3-year ramp up to 50ktpa Target Capacity by 2030
50 ktpa
Phase 1
Phase 2
Capacity Available
37.5 ktpa
Capacity Available
25 ktpa
12.5 ktpa
Capacity Available
Capacity Available
2027
Q1
Q2
Q3
2028
Q4
Q1
Q2
Q3
2029
Q4
Q1
Q2
Q3
2030
Q4
Q1
Q2
Q3
2031+
Q4
Q1
Q2
Q3
Q4
Significant Resource Growth
True Scale of
Deposit is Emerging
Resource expansion to 8.1 million tonnes LCE
from January 2023 update:
Resources in Million Tonnes LCE
8.1
§ Measured resource has increased ~37% from 1.6 to 2.2 million tonnes LCE
§ Indicated resource has increased ~24% from 0.58 to 0.72 million tonnes LCE
§ Inferred resource has increased ~67% from 3.1 to 5.2 million tonnes LCE
Exploration Target:
5.3
4.4
5.2
3.1
3.4
2.2
1
2018
Jan-23
Measured & Indicated
2.9
Jun-23
Inferred
Note: Numbers are based on information in Lake’s JORC
update announced on 15 June 2023 . All material
assumptions continue to apply and have not materially
changed.
1. Not an actual ‘production target’ (as defined in the ASX
Listing Rules), which is subject to completion of a bankable
DFS.
§ High: 21.8 million tonnes LCE
§ Low: 5.2 million tonnes LCE
Positive outcomes from the above exploration and evaluation activities will support Lake
Resources’ business plan to deliver target plant capacity of 50,000 tpa of lithium carbonate1.
Note: The potential quantity and grade of an exploration target is conceptual in nature, there
has been insufficient exploration to determine a mineral resource and there is no certainty
that further exploration work will result in the determination of mineral resources or that a
production target itself will be realized.
14
Additional Lithium Discovery
New brine found north and south of
previously measured resource
§ 283 mg/L at K22 in northern expansion area
§ 219 mg/L at K21 in southern expansion area
§ K21 is shallow and may have better grades at depth
§ Infilling necessary for higher confidence (i.e., indicated and
measured)
§ Plant design is based on grade 205mg/L
Project grade brine discoveries at planned reinjection areas.
Extends lateral extent of reservoir beyond previous internal
estimates.
15
Successful Extraction and Reinjection
Demonstrated extraction and reinjection in the
resource area
§ Tested upper reservoir
§ High reservoir permeability
§ Extrapolates to high well production rates
Water storage
between wells
KB
(Injection Point)
(~65 liters per second)
Indicative of high conversion rates from
resource to reserve
Proven Injectivity
§ Injected >12 million liters at KC
§ Injected >19 million liters at KB
First successful reinjection in Catamarca Province
Pipeline to KC
(Extraction Well)
16
DLE Process Proven
Major Milestones Achieved in
Kachi Demonstration Plant using
Lilac DLE Technology
Process flow sheet proven from brine
to battery grade lithium carbonate
§ DLE demonstration plant continuously operational for more than
§
§
§
§
§
1. Extraction Brine Buffer Pond2
2. Depleted Brine Buffer Pond2
3. Lilac Ion Exchange
4. Carbonation and Product Storage
5. Chlor-Alkali & Reagents
2,500 hours with 90% uptime
Highly selective process with consistent results on sample
testing
§ > 90% impurity removal
§ > 80%1 lithium recovery
Produced 120,000 liters of eluate containing more than 2,500kg
of LCE
Lithium Carbonate exceeds battery grade requirements > 99.8%
purity
Initial offtake samples shipped
Lithium carbonate demonstration plant currently producing
Notes:
1. For DLE recovery only; >76% for total plant
2. Buffer pond size for our target 50Ktpa plant capacity is more than 100x smaller than
evaporation ponds required for same output
17
Project Kachi
Next Steps
18
Next Six Months
Reservoir
§ Completion of DFS Field Test Work (end of pumping)
§ Complete Groundwater Model
Lithium Carbonate
Demo Plant
§ Completion of demo plant test work
EPCM
§ Select FEED / EPCM Contract Partner
Bankable DFS
§ DFS for Phase 1 Complete
Power
§ Power solution selected
Funding
§ Data room open for ECA backed Debt project stakeholders
Offtake
§ Commence negotiations on binding Offtake agreements
EIA
§ Preparation for submission of EIA in Q1 2024
19
Positioned for Success
Credible, Achievable and De-risked
Significant
Resource Growth
§ Potential resource expansion to 8.2 million tonnes LCE
§ ~40% increase in Measured and Indicated Resource and 67% increase in Inferred
Resource
§ Higher lithium grades from new discoveries
§ Brine footprint expanding horizontally and vertically. DFS timing is consistent with
increasing reserves base
Achievable Timeline
to Lithium Production
§ Proven DLE technology
§ Significant progress with power solution
§ Visibility to First Lithium with clear milestones
Phased Approach
to Production
§ Phased approach of 2 x 25Ktpa plants de-risks project execution
§ Accelerates first commercial lithium carbonate production
§ Managing Infrastructure and logistics
§ High level of management expertise and exceptional quality standards
20
Thank you!
Share your feedback